New Shop Plans

As of last summer (2011), plans for the new shop were put on hold indefinitely after our commercial liability insurance premiums increased substantially, forcing us to give up the insurance coverage and shut down our service & repair business. As of now (April 22, 2012) we are concentrating our efforts on our mail order businesses and looking for affordable, commercial farm insurance so we can take our family farm commercial. Our power sports business and plans for a new shop are still alive – simply in a state of dormancy until we can work out a viable and affordable commercial liability insurance plan that better fits the size of our business (and wallet).

Drawings for the new shop have been developed. Site work (land clearing and ground-breaking) began the end of last November. Land clearing  (cutting trees and clearing brush) has progressed slowly over the Winter and continues as time and weather conditions allow. This is where you will find updates and progress photos as work continues. The new shop drawings are posted here, and building site photos will appear here as they are available. If you have any comments or suggestions, please drop me an email (contact page).

The image shown below is of the proposed floorplan for the new Downeast Thunder shop (posted Oct 6th, 2009):

New Shop Floor Plan

The next picture is a drawing of the proposed new shop’s front elevation (posted 26 OCT 2009):

Downeast Thunder Front Elevation

Downeast Thunder Front Elevation

Next Picture shows the right side elevation:
Right Side Elevation

Right Side Elevation

Next pictures are of the rear elevation and left side elevation (posted 11/02/09)

Rear Elevation

Rear Elevation

Left-Side-Elevation-Layout4

The final drawing is of the plot plan where the new Downeast Thunder shop will be built:
Plot-Plan-Layout5
From this point on, you’ll find photos of the building site, posted as they become available, along with notes regarding progress & other updates:
Photo of the building site for the new Downeast Thunder Shop – clearing will begin this weekend (posted 6 NOV 09):
Building Site for new Downeast Thunder Shop

Building Site for new Downeast Thunder Shop

New Shop Building Site 9 March 2010

Land clearing progress on new shop site – 9 March 2010
June 16th, 2010 update: The land for the new shop has been cleared and was finshed over the past two days by a local logging company (Deane Young Logging Co.). The next three photos shows some of their handywork along with machine used to do the job. Now that the site has been cleared of trees, the ground work commences. First off – we have to begin removing the tree stumps.

Shop site cleared 6/16/2010

6/16/2010 "Extreme Chainsaw"

6/16/2010 Cleared 3 acres in less than 2 days.